Reconstruction of cooling tower

[ Year: 2012 ]

[ Country: Ukraine ]

[ Industry: Energy industry ]

About project:

from November 2011 until June 2012 our experts had carried out works to replace a wood sheathing of the cooling tower on metal sheathing and its partial coloring, as well as strengthening of metal structures.

Implementation:

To restore the cooling capacity of the cooling tower to the nominal parameters and enhance this efficiency of the turbines its reconstruction had been carried out. From November 2011 until June 2012 our experts had carried out works to replace a wood sheathing of the cooling tower on metal sheathing and its partial coloring,  as well as strengthening of metal structures. Works had been executed with high quality and on time.

Result:

all works were completed in accordance with the regulations, in full scope, and within the established timeframe.

feedback

Need a consultation?

Fill out the form - and we will contact you shortly.