project implementation period reduced to 4 calendar days.
Implementation:
dismantling of the lining: shotcrete and masonry. Layer thickness 280 mm, area 80 m2;
cleaning the furnace from dismantled lining (more than 22 tons);
dismantling 33 burner stones and burners;
surface preparation and installation of lining fasteners;
installation of lining 80 m2 (about 700 modular blocks of ceramic fiber);
installation of 33 burner stones, 66 insulation blocks and 33 burners.
Result:
the work was completed in full, ahead of schedule by 15%. The customer obtained significant energy savings after replacing the lining with a modern lightweight ceramic fiber lining.