Thermal insulation of the RKF-35 steam boiler, gas ducts and pipelines
[ Year: 2021 ]
[ Country: Ukraine ]
[ Industry: Food industry ]
Task:
Thermal insulation of the steam boiler RKF-35, equipment, gas ducts and pipelines of the boiler room.
Implementation:
supply of basic and auxiliary working materials;
manufacturing and installation of anchors and bandages for fastening thermal insulation materials;
installation of thermal insulation plates on flat surfaces;
installation of thermal insulation of pipelines of various diameters with thermal insulation mats and basalt cylinders, followed by installation of a protective layer of galvanized steel;
pouring refractory concrete into boxes and hatches;
installation of thermal insulation from mineral wool mats and ceramic fiber mats according to the customer's project;
manufacturing and installation of support structures for fastening the boiler sheeting;
anti-corrosion coating of supporting structures with heat-resistant enamel;
installation of sheathing from corrugated sheet and flashings from steel sheet with a polymer coating 0.7 mm thick;
supply and installation of soft thermal insulation covers for flanged connections and stop valves of pipelines.
Result:
The work was performed at a high level, on time and in full, according to the customer’s project.