Result:
all works were completed in accordance with the regulations, in full scope, and within the established timeframe.
From February till July 2012 the specialists of our company carried out the works on insulation of the electric filter framework. As an insulating layer the customer selected boards based on basalt fiber. As a protective layer the zinc-coated steel sheet had been used.
all works were completed in accordance with the regulations, in full scope, and within the established timeframe.